Project Details
Previous slide
Next slide
MO-1 Tengiz Facilities
Construction of 2Nos single storey mechanical and storage shops, 750m2 each, including 10T overhead cranes along with 1No. two storey office building with an area of 1,400m2. In addition, support facilities: 5,000L Water Storage tank with required equipment and fittings and Electrical room equipped with an emergency generator.
Location
Tengiz, Atyrau, Kazakhstan
Client
MO-1 Company, main contractor for Tengizchevroil LLC.
Project
Construction Support Base
Scope
Design, Engineering, Procurement, Construction and Commissioning.
Duration
8 Months
Total built-up area
3,400 m2
Total Parking Area
1,400 m2
Total commercial and administrative area:
1,400 m